ECHO Arena

 

Covering an area 18,000 square metres, the specialist imported parting from china was brought in by boat via Southampton, and stored at Marshalls depot in Alconbury in Cambridge.

The works commenced in August 2007, and were initially due for completion in February 2008, however a sectional handover of the building produced a staged completion process extending the contract by a further six months.

Over fifteen operative gangs of tradesmen were engaged in the construction of the hard landscaping package and were supervised by our team of project managers, site supervisors, project engineers, foremen and gang leaders.

A logistical approach to working around the other sub-contractors engaged on the site had to be adopted, and numerous co-ordination meetings took place on a regular basis, to ensure that all works were co-ordinated efficiently. Progress on the site, in the critical months, was ensured by seven day working with twilight shifts being undertaken to maintain laying progression. Dowhighs works throughout the whole hard landscaping package included:

i) Earthworks and drainage

ii) Ducting for street lighting and CCTV

iii) Manhole and duct box construction

iv) Co-ordination of waterproofing and specialist sub-contractors

v) Bituminous and concrete overlay to external works areas

vi) Amphitheatre and staircase construction

vii) Granite, conservation and Yorkstone paving, seats and kerbing.

Go Back To Content
Project Title
Liverpool ECHO Arena & Convention Centre

Value
£ 2.35m

Duration
12 Months

Date
August 2007 to August 2008

Project Manager
Neil Hayes

Client
Liverpool City Council

     