Project Overview The programme of works has been to install override to Braydon Close –week commencing 22nd June excavating existing kerbs and laying new kerbs and edgings on both sides of the central grassed area began. And will be completed by Friday 10th July. Project Details Date: June / July 2020 Location: Liverpool, Merseyside Client:…

Read More

Project Overview Coastal road North Phase, shore  road to weld road, the ongoing installation of 3.5km new filter drain, pipe bedding, and type A and type B filter material. All designed to improve the drainage of both the land within the SSSI land, the discharge of the high tide and the carriageway surface water. Project…

Read More
fine janes brook footpath installation by Dowhigh

Project Overview The ongoing installation of a new 3m wide concrete footway /cycle ways. A length of 600m running behind the Southport Hospital, and connects Scarisbrick New Road and Town Lane. Project Details Date: Ongoing – June 2020 Location: Southport, Merseyside Client: Sefton Borough Council

Read More
resurfacing footpaths and digging groundworks on the coastal road southport

Project Overview Part of the East / West Cycle Link for Sefton MBC, valued at approx. £1.7m, The Coastal Road works involve the removal of the existing filter material and installing over 3000m of 225mm dia pipe, within over 2000t of pipe bedding, over 8000t of Type B material wrapped in a terram 1000 matting,…