The new signal junction at the Coronation Road / A565 junction at Crosby town centre will provide improved and safer crossings facilities for all users to and from the town centre.
The traffic signal Contractors had been working to a timetable with an expected operational date of this week.
Stringent testing of the new signalling equipment has identified a small number of necessary reconfigurations to ensure the system works efficiently for our road users.
Once these configurations have been made the equipment will be made operational, which contractors expect to be on Monday December 11th.
The current temporary closure at the Coronation Road / A565 junction and the temporary one-way on Vale Road and Harrington Road will remain in place until the signals are switched on.
We apologise for any inconvenience this may cause.