Priory Road, Anfield

Start Date: 21st October 2024
Timescales: Approximately 8 months

UPDATE: 17th December 2024

Road closures will be removed on Friday 20th December until 6th January 2025.

Phase 2 (BP garage to crematorium) will commence on the 6th January 2025.

Scheme Overview

Works location: The full length of Priory Road, between the junctions of Utting Avenue and Walton Lane

Length of works: Approximately 800m

Scope of works: New drainage system, new pedestrian crossing near the crematorium, new footways and carriageway reconstructions

PLEASE NOTE: All businesses within the scope of the works will remain open as usual, and access will be maintained via Walton Lane.

Important Information

During works, Priory Road will be fully closed between Monday to Friday, excluding for services to the crematorium and emergency access.

Diversions will be fully signposted and diversion plans will be advised once in place.

For parking on matchdays please contact either Liverpool FC or Everton FC directly, who will advise on car and coach parking as well as walking routes and access to the grounds during these times.

Works Phasing

Phase 1: Utting Avenue to BP garage

Phase 2: BP garage to crematorium

Phase 3: Crematorium entrance (night works)

Phase 4: Crematorium entrance to Walton Lane

Phase One – works and traffic management plan (click to to open in new window)

Phase Two – works and traffic management plan (click to open in new window)

Phase Three – works and traffic management plan (click to open in new window)

Phase Four – works and traffic management plan (click to open in new window)

Matchday – Access and Egress Plans (click to open in new window)